Floor Shift Lever ASSY (MTM): Replacement
WARNING: This page is about a different variant/trim than selected.
- REMOVE KNOB SUB-ASSY, SHIFT LEVER
- REMOVE INSTRUMENT CLUSTER FINISH PANEL ASSY CTR (See REPLACEMENT )
- REMOVE INSTRUMENT PANEL BOX (See REPLACEMENT )
- REMOVE INSTRUMENT PANEL FINISH PANEL LOWER CENTER (See REPLACEMENT )
- DISCONNECT FLOOR SHIFT CABLE TRANSMISSION CONTROL SHIFT
- Remove the clip and washer and disconnect the cable end of the shift cable from the shift lever assy.
- Turn the lock and disconnect the shift cable from the shift lever assy.
- DISCONNECT FLOOR SHIFT CABLE TRANSMISSION CONTROL SELECT
- Remove the clip and disconnect the cable end of the select cable from the shift lever assy.
- Turn the lock and disconnect the select cable from the shift lever assy.
- REMOVE FLOOR SHIFT LEVER ASSY
- Remove the 4 nuts and shift lever assy.
- INSTALL FLOOR SHIFT LEVER ASSY
- Install the shift lever assy with the 4 nuts.
- Torque: 12 N.m (120 kgf.cm, 9 ft.lbf)
- Install the shift lever assy with the 4 nuts.
- CONNECT FLOOR SHIFT CABLE TRANSMISSION CONTROL SHIFT
- Connect the shift cable with the clip to the shift lever assy.NOTE:
- The projecting part of the cable outer should face upward when the shift cable is installed.
- Make sure that after installation the cable outer spring is moved to the place shown in Fig 7 .
- Connect the shift cable end as shown in Fig 8 .
- Install the washer and clip.
- Connect the shift cable with the clip to the shift lever assy.
- CONNECT FLOOR SHIFT CABLE TRANSMISSION CONTROL SELECT
- Connect the select cable with the clip to the shift lever assy.NOTE:
- The projecting part of the cable outer should face upward when the shift cable is installed.
- Make sure that after installation the cable outer spring is moved to the place shown in Fig 9 .
- Connect the select cable end with the clip.
- Connect the select cable with the clip to the shift lever assy.