Installation [10/2020 - ]: Procedure
- INSTALL NO. 6 ENGINE COVER
Refer to PROCEDURE - Step 31
- INSTALL TIMING CHAIN COVER ASSEMBLY
Refer to PROCEDURE - Step 32
- INSTALL CRANKSHAFT TIMING GEAR OR SPROCKET
Refer to PROCEDURE - Step 33
- INSTALL NO. 2 CHAIN VIBRATION DAMPER
Refer to PROCEDURE - Step 34
- INSTALL NO. 1 CHAIN VIBRATION DAMPER
Refer to PROCEDURE - Step 35
- INSTALL IDLE SPROCKET ASSEMBLY
Refer to PROCEDURE - Step 36
- INSTALL NO. 1 CHAIN SUB-ASSEMBLY
Refer to PROCEDURE - Step 37
- INSTALL CHAIN TENSIONER SLIPPER
Refer to PROCEDURE - Step 38
- INSTALL NO. 1 CHAIN TENSIONER ASSEMBLY
Refer to PROCEDURE - Step 39
- INSPECT VALVE TIMING
Refer to PROCEDURE - Step 40
- INSTALL OIL PUMP DRIVE CHAIN SUB-ASSEMBLY
- Rotate the crankshaft timing gear key position 30° counterclockwise as shown in the illustration.
*1 Oil Pump Drive Sprocket *2 Oil Pump Drive Shaft Sprocket *3 Oil Pump Drive Chain Sub-assembly *a Mark Plate *b Timing Mark *c D Cut Plane - Set the D cut plane of the oil pump shaft at the position shown in the illustration.
- Align the mark plates (yellow) on the oil pump drive sprocket, oil pump drive shaft sprocket and oil pump drive chain sub-assembly with the timing marks.
- Install them to the oil pump shaft and crankshaft.
- Temporarily install the oil pump drive shaft gear nut.
- While pushing the chain damper spring, install the chain tensioner plate and chain damper spring.
- Using the hexagonal portion of the camshaft, secure the camshaft.
- Tighten the oil pump drive shaft gear nut.
Torque: 36 N*m (367 kgf*cm, 27 ft.*lbf)
- Rotate the crankshaft timing gear key position 30° counterclockwise as shown in the illustration.
- INSTALL TIMING CHAIN OR BELT COVER SUB-ASSEMBLY
- Remove any old packing remaining on the sealing surfaces before applying seal packing.
- Clean the contact surfaces of the timing chain cover assembly, timing chain or belt cover sub-assembly and confirm that there is no oil, moisture or other foreign matter on the surfaces.
*a Timing Chain Cover Assembly Side *b Timing Chain or Belt Cover Sub-assembly Side Clean and Degrease - - NOTE:- Be sure to clean and degrease the contact surfaces, especially the surfaces indicated in the illustration.
- Check the bolts and bolt holes, and clean and degrease them.
- Install 2 new water pump gaskets to the timing chain cover assembly.
- Apply seal packing in a continuous line to the timing chain or belt cover sub-assembly as shown in the illustration.NOTE:
- Using non-residue solvent, clean and remove any oil from the installation surface.
- Check the bolts and bolt holes, and clean and degrease them.
- Install the timing chain or belt cover sub-assembly within 3 minutes and tighten the bolts within 15 minutes of applying seal packing.
- Do not add engine oil for at least 2 hours after installing the timing chain cover assembly.
- Do not start the engine for at least 2 hours after installing the timing chain cover assembly.
*a Standard Seal Packing Diameter
3.0 to 4.0 mm (0.118 to 0.157 in.)*b Seal Packing Width 35 mm (1.38 in.) *c Thick Coating Cross-section *d Wide Seal Packing Diameter
4.0 to 8.0 mm (0.157 to 0.314 in.)*e Wide Seal Packing Diameter
3.0 to 5.0 mm (0.118 to 0.197 in.)Seal Packing - Temporarily install the timing chain or belt cover sub-assembly with the 27 bolts.
*a Type of bolt *b Tightening Order Bolt Length
Item Length A 35 mm (1.38 in.) B 80 mm (3.15 in.) C 90 mm (3.54 in.) D 55 mm (2.17 in.) NOTE:Make sure that there is no oil on the bolt threads.
- Tighten the 27 bolts in several steps, in the sequence shown in the illustration.
Bolts A, B and D
Torque: 29 N*m (296 kgf*cm, 21 ft.*lbf)
Bolt C
Torque: 43 N*m (438 kgf*cm, 32 ft.*lbf)
- INSTALL TIMING CHAIN CASE OIL SEAL
Refer to PROCEDURE - Step 1
- INSTALL CRANKSHAFT PULLEY
Refer to PROCEDURE - Step 2
- INSTALL CRANKSHAFT DAMPER SUB-ASSEMBLY
Refer to PROCEDURE - Step 3
- INSTALL CAM TIMING OIL CONTROL SOLENOID ASSEMBLY LH (for Exhaust Side of Bank 2)
Refer to PROCEDURE - Step 1
- INSTALL CAM TIMING OIL CONTROL SOLENOID ASSEMBLY LH (for Intake Side of Bank 2)
Refer to PROCEDURE - Step 2
- INSTALL CAM TIMING OIL CONTROL SOLENOID ASSEMBLY RH (for Exhaust Side of Bank 1)
Refer to PROCEDURE - Step 1
- INSTALL CAM TIMING OIL CONTROL SOLENOID ASSEMBLY RH (for Intake Side of Bank 1)
Refer to PROCEDURE - Step 2
- INSTALL SPARK PLUG TUBE GASKET
Refer to PROCEDURE - Step 54
- INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY RH
- Install a new No. 1 cylinder head cover gasket RH to the cylinder head cover sub-assembly RH.
- Install 6 new No. 2 cylinder head cover gasket RH to the cylinder head cover sub-assembly RH.
- Before applying seal packing black, cleanly remove any old sealant sticking to the part to be sealed.
- Remove any remaining seal packing material and be careful not to drop any oil on the contact surfaces of the cylinder head sub-assembly, timing chain cover assembly and cylinder head cover sub-assembly.
- Apply seal packing as shown in the illustration.
Seal packing
Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
NOTE:- Remove any oil from the contact surface.
- Install the cylinder head cover sub-assembly within 3 minutes and tighten the bolts within 15 minutes after applying seal packing.
*a Application Range *b Protrusion HINT:
Area Seal packing diameter Continuous Line Area 4.0 to 7.0 mm (0.157 to 0.276 in.) Diagonal Line 3.0 to 6.0 mm (0.118 to 0.236 in.) - Install a new camshaft bearing cap oil hole gasket RH to the camshaft bearing cap.
- Degrease the threads of the 13 cylinder head cover installation bolts (A).
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
Bolt A Bolt B - Install the new 2 O-rings to the 2 VVT sensors.
Refer to INSTALLATION [12/2017 - ]
- Temporarily install the 2 VVT sensors with the 2 new bolts (B).
- Temporarily install the cylinder head cover sub-assembly RH with the 13 bolts (A).
- Temporarily install the cylinder head cover sub-assembly with the 15 bolts. Tighten the bolts uniformly in several steps.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
Bolt Length
Item Length Bolt A 23.5 mm (0.925 in.) Bolt B 30 mm (1.18 in.) NOTE:Do not start the engine for at least 2 hours after installation.
- Install the No. 1 intercooler air guide to the cylinder head cover sub-assembly RH.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY LH
- Install a new No. 1 cylinder head cover gasket LH to the cylinder head cover sub-assembly LH.
- Install 6 new No. 2 cylinder head cover gasket LH to the cylinder head cover sub-assembly LH.
- Before applying seal packing black, cleanly remove any old sealant sticking to the part to be sealed.
- Remove any remaining seal packing material and be careful not to drop any oil on the contact surfaces of the cylinder head sub-assembly, timing chain cover assembly and cylinder head cover sub-assembly LH.
- Apply seal packing as shown in the illustration.
Seal packing
Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
NOTE:- Remove any oil from the contact surface.
- Install the cylinder head cover sub-assembly LH within 3 minutes and tighten the bolts within 15 minutes after applying seal packing.
HINT:
Area Seal packing diameter Continuous Line Area 4.0 to 7.0 mm (0.157 to 0.276 in.) Diagonal Line 3.0 to 6.0 mm (0.118 to 0.236 in.) - Install a new camshaft bearing cap oil hole gasket LH to the camshaft bearing cap.
- Degrease the threads of the 13 cylinder head cover installation bolts (A).
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
Bolt A Bolt B - Install the new 2 O-rings to the 2 VVT sensors.
Refer to INSTALLATION [12/2017 - ]
- Temporarily install the 2 VVT sensors with the 2 new bolts (B).
- Temporarily install the cylinder head cover sub-assembly RH with the 13 bolts (A).
- Temporarily install the cylinder head cover sub-assembly LH with the 15 bolts. Tighten the bolts uniformly in several steps.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
Bolt Length
Item Length Bolt A 23.5 mm (0.925 in.) Bolt B 30 mm (1.18 in.) NOTE:Do not start the engine for at least 2 hours after installation.
- Install the No. 1 intercooler air guide to the cylinder head cover sub-assembly LH.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- INSTALL SPARK PLUG
Refer to PROCEDURE - Step 1
- INSTALL OIL FILTER BRACKET SUB-ASSEMBLY
- Install 2 new gaskets to the timing chain cover assembly.
- Install the oil filter bracket sub-assembly with the 3 bolts.
Torque: 21 N*m (214 kgf*cm, 15 ft.*lbf)
- INSTALL IGNITION COIL ASSEMBLY
Refer to PROCEDURE - Step 2
- INSTALL GENERATOR BRACKET SUB-ASSEMBLY
Refer to PROCEDURE - Step 49
- INSTALL WATER INLET ASSEMBLY
Refer to PROCEDURE - Step 4
- INSTALL V-RIBBED BELT TENSIONER ASSEMBLY
Refer to PROCEDURE - Step 7
- INSTALL IDLER PULLEY SUB-ASSEMBLY
Refer to PROCEDURE - Step 8
- INSTALL WATER PUMP PULLEY
Refer to PROCEDURE - Step 9
- INSTALL WATER HOSE
Refer to PROCEDURE - Step 9
- CONNECT NO. 4 RADIATOR HOSE
Refer to PROCEDURE - Step 12
- INSTALL WATER OUTLET PIPE WATER BY-PASS JOINT
Refer to PROCEDURE - Step 78
- INSTALL NO. 2 WATER OUTLET PIPE
Refer to PROCEDURE - Step 79
- INSTALL NO. 1 WATER OUTLET PIPE
Refer to PROCEDURE - Step 80
- INSTALL NO. 11 ENGINE WIRE
Refer to PROCEDURE - Step 7
- INSTALL NO. 2 WATER BY-PASS PIPE SUB-ASSEMBLY
Refer to PROCEDURE - Step 8
- INSTALL WATER CONTROL VALVE
Refer to PROCEDURE - Step 1
- INSTALL INTAKE PIPE STAY
Refer to PROCEDURE - Step 7
- INSTALL NO. 1 TURBO PRESSURE SENSOR
Refer to PROCEDURE - Step 2
- CONNECT NO. 1 WATER BY-PASS PIPE
- Connect the No. 1 water by-pass pipe with the 3 bolts.
Torque: 21 N*m (214 kgf*cm, 15 ft.*lbf)
- Connect the No. 1 water by-pass pipe with the 3 bolts.
- CONNECT NO. 1 TURBO WATER PIPE SUB-ASSEMBLY
- Connect the No. 1 turbo water pipe sub-assembly to the cylinder head cover sub-assembly RH with the bolt.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- Connect the No. 1 turbo water pipe sub-assembly to the cylinder head cover sub-assembly RH with the bolt.
- INSTALL TURBO WATER PIPE STAY
- Install the turbo water pipe stay with the 2 bolts.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- Install the turbo water pipe stay with the 2 bolts.
- INSTALL NO. 2 AIR INLET DUCT
- Connect the No. 2 air inlet duct to the compressor inlet elbow.
- Tighten the hose clamp.
Torque: 4.0 N*m (41 kgf*cm, 35 in.*lbf)
- Install the bolt.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- Attach the 2 clamps and connect the vacuum hose.
- CONNECT NO. 2 PCV TUBE
Refer to PROCEDURE - Step 19
- INSTALL NO. 1 AIR HOSE
- Install the No. 1 air hose to the No. 1 compressor outlet elbow.
- Tighten the hose clamp.
Torque: 6.3 N*m (64 kgf*cm, 56 in.*lbf)
- INSTALL NO. 1 AIR INLET DUCT
- Connect the No. 1 air inlet duct to the compressor inlet elbow.
- Tighten the hose clamp.
Torque: 4.0 N*m (41 kgf*cm, 35 in.*lbf)
- Install the bolt.
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- Attach the 2 clamps and connect the vacuum hose.
- CONNECT NO. 1 PCV TUBE
Refer to PROCEDURE - Step 20
- INSTALL ENGINE OIL LEVEL DIPSTICK GUIDE
Refer to PROCEDURE - Step 23
- INSTALL FUEL PUMP ASSEMBLY (for Bank 2)
Refer to INSTALLATION [10/2020 - ]
- INSTALL FUEL PUMP ASSEMBLY (for Bank 1)
Refer to INSTALLATION [10/2020 - ]
- INSTALL GENERATOR ASSEMBLY
Refer to INSTALLATION [10/2020 - ]
- INSTALL COMPRESSOR ASSEMBLY WITH PULLEY
- For 2WD:
Refer to INSTALLATION [12/2017 - 11/2021] , or refer to INSTALLATION [11/2021 - ]
- For AWD:
Refer to INSTALLATION [12/2017 - 11/2021] , or refer to INSTALLATION [11/2021 - ]
- For 2WD: